6.2.1. Before commencing concreting work, the employer shall:
(a)  obtain from an engineer:
i.  a signed and sealed declaration attesting that the work complies with all the points in the shoring drawing filed; and
ii.  the authorization to proceed with the concreting work;
(b)  transmit immediately a copy of the declaration to the Commission; and
(c)  keep a copy of such declaration at the work site.